Mount Royal Avenue and Dolphin Street, Baltimore, Md
|
Construction process: The whole construction or building process took 21/2 weeks. The Untitled (compass) was sited due North - directly relating the Domestic's interrelationship with the sun's path. The MACAC staff prepared the site for the 4 inch concrete pad. I let the pad set for about five days. The structure armature posts, lintels and beams were pre-cut at Rubeling & Kain Studios. The erecting process took about 2 1/2 hours on site. The wall panel prototype was designed on site and were installed over the course of a week. The roof and center rotating planes were the last parts of the site to be installed. The amount of visitors at ARTSCAPE prohibited animating all of the wall planes. |